The Five Things Shops Underestimate When Quoting Brass

Published September 25, 2026. Reviewed for the facts in the corrections log.

Brass cuts predictably, so the margin on a brass job leaks elsewhere. The usual five are the burr inside a bore at a cross hole, gauging on sealing threads, a bar price that tracks copper weekly, lead-free grades priced as a single uplift and per lot certificates. State every assumption in the quote and decline parts outside your band.

Brass is rated 100 for machinability, the benchmark every other metal is measured against. That reputation is exactly why brass quotes go wrong. The cutting is the easy, predictable part, and it is not where the money leaks.

Here are the five that catch shops out, in rough order of how much they cost.

1. The burr nobody put on the drawing

This is the big one.

On a fitting, the burr that matters is not on an outside edge. It is inside a bore, at the intersection where a cross hole breaks through, where nobody can see it and few tools can reach it.

The problem is that it rarely appears on the drawing. A note saying “deburr all edges” reads as external edges, so you quote a tumble, and the tumble does nothing for an internal intersection.

Then the first article comes back, or worse, the parts pass at your end and fail a leak test after assembly at theirs. Now you are adding an operation to a price that is already fixed.

What to do at quote time: ask the buyer explicitly what internal burr condition they need, before you price. If the drawing is silent, say in your quote what you have assumed. “Quoted with external deburr only, no internal deburring at cross hole intersections” is a sentence that protects you and starts a useful conversation. Detail in the burr inside the bore.

2. Gauging sealing threads

A thread on a drawing costs one line of code. A sealing thread costs a tool, a pass, a gauge and a scrap risk.

Tapered pipe threads are the expensive case. The check is a go and no-go ring or plug gauge measuring standoff, not a micrometer, and a part that is out is scrap rather than rework because you cannot put material back.

If the drawing does not state a class and a gauge standard, you are being asked to guess at an inspection regime. Quote to a stated assumption or ask. See thread standards on brass fittings.

3. The metal price

Brass is 60 to 70 percent copper by weight and bought by weight, so the bar price tracks a commodity that moves weekly.

On a small Swiss turned part this is noise. On a heavy valve body the metal can be more than half the price before a tool touches it, and a quote you honour three months later can be underwater on material alone.

Two habits worth having. Put a validity period on every quote and make it short on heavy parts. And on repeating work, propose a metal price basis, where the conversion element is fixed for the contract and the metal element is recalculated against a published index at agreed intervals. Buyers in this industry understand that structure and it removes the argument from every repeat order. See why brass quotes expire.

4. Lead-free is two adjustments, not one

If the part is a potable water component it is going to be C69300 silicon brass or a bismuth brass, not C360.

Quote it as two separate lines.

Cycle time. Published machinability near 80 against C360 at 100, so expect roughly a fifth more time. Silicon brass also work hardens, so if you have not run it before, budget the learning rather than pricing it as C360 with a small uplift.

Material. Costs more per kilo and is held by fewer stockists, which sometimes means a longer lead time on an unusual diameter as well as a higher price.

Buyers who see a single lumped premium assume it is margin and push back. Buyers who see two lines understand it. See leaded and lead-free brass compared.

Turn brass every week? Apply as a partner shop

5. Certificates and traceability

“Material certificate required” is cheap. “Material certificate with every lot” is not.

Per lot certification forces material segregation through your whole process: bar batches kept separate, records of which parts came from which bar, and that trail held through machining, finishing and packing. That is real operational cost and it belongs in the price.

Ask which one they need. Most buyers who tick the box have not thought about the difference, and many only need it on the first article. See material certificates for brass parts.

The quote note that saves the most argument

Most brass drawings arrive missing the same handful of things. Rather than guessing silently, state your assumptions in the quote.

Quoted on the following assumptions:
- External deburr only. No internal deburring
  at cross hole intersections.
- Threads to stated class, gauged on first
  article only.
- Material certificate with first article, not
  per lot.
- Price valid 30 days, subject to metal price
  at order date.

Five lines. They cost nothing, they make your number comparable to a competitor who assumed differently, and they turn a later dispute into a change order rather than an argument.

Deciding not to quote

The fastest way to improve the return on your estimating time is to decline more.

A part that belongs on a Swiss lathe, quoted honestly on your machining centre, will come back several times the market price. You will lose it. The only thing that changed is that you spent an hour.

Knowing your band and saying no outside it is not lost business. It is the same discipline that decides whether taking on extra enquiries pays.

Turn brass regularly? Apply as a partner shop. We send work requests with the part, alloy, quantity and compliance requirement on them, you quote us and you can decline in ten seconds. No fee to join.

Frequently asked questions

Why do brass jobs lose money when the cycle time was right?

Almost always deburring, and almost always inside a bore. The cycle time on a bar-fed lathe is predictable and easy to quote. The hand work on a cross hole that breaks into a bore is not on the drawing, does not appear in the CAM simulation, and is discovered on the first article after the price is fixed.

Should I quote a metal price adjustment clause?

On anything heavy, yes. Brass is 60 to 70 percent copper by weight and the bar price moves weekly. On a small turned part the metal is noise and a fixed price is fine. On a valve body the metal can be more than half the quote, and absorbing a copper move on a repeat order means working at a loss you did not agree to.

How should I price a lead-free brass job against C360?

Two separate adjustments. Cycle time goes up roughly a fifth, because published machinability is near 80 against C360 at 100. The bar costs more per kilo and is held less widely, which can also mean a longer lead time. Quote them as two lines, because buyers who see one lumped premium assume it is margin.

Is it worth quoting a part outside my normal band to fill a gap?

Occasionally, and quote it as what it is. A part that belongs on a Swiss lathe quoted honestly on your machining centre will be several times the market price and you will lose it, which costs you an estimator hour. Deciding not to quote is a legitimate answer and a fast one.

Alloys in this guide

AlloyLead %Mach.DZR
C360 free-cutting brassC36000 · CuZn36Pb3 / CW603N2.5 to 3.7100Poor
C69300 silicon brassC69300 · CuZn21Si3P / CW724Runder 0.0980High
Bismuth brassC49300 / C49350 · No single EN equivalent, see supplier specunder 0.2580Moderate

Published typical values for the alloy. Machinability against C360 at 100. Not a promise from a shop.

Sources

  1. Wikipedia, Machinability en.wikipedia.org
  2. Copper Development Association copper.org

Turn brass every week?

Brass CNC Parts sends brass work requests and nothing else. We are your customer: you quote us and we place the purchase order. No fee to join.

We reply within 24 business hours and ask for the rest then. Or use the full form.

Keep reading

Get a quote